Results timeline
The achieved results of the iSTORMY project are displayed on the timeline below. Results are ordered by month from the project start in December 2020 (month 1) to the project completion in May 2024 (month 42). If you would like to keep updated, please subscribe to the iSTORMY newsletter. Newsletters will be issued twice a year.
Click here to view reports of planned actions of the project.
Progress of WP4: self-healing EMS

Result from partner MPEG and coordinator VUB in April 2023, month 27 of the project.
Progress of WP2: Finalizing the hybrid battery pack

Result from partners TNO, CEGASA and CEA in November 2022, month 22 of the project
Milestone 3 (achieved) : Battery pack and PE interface architecture defined

Result has been achieved by coordinator VUB on 30 November 2021 in month 12 of the project.