February 24, 2022 Progress of WP2: Working towards the fourth milestone of the project After an extensive set of battery cell performance testing on four different types of battery cells of different chemistrie. Read more
December 9, 2021 Milestone 3 (achieved) : Battery pack and PE interface architecture defined Result from coordinator VUB. The result has been achieved on 30 November 2021 in month 12 of the project (results documented in Work Package 3: Modular Power Electronics interfaces). The… Read more
August 19, 2021 Milestone 2 (achieved) : Testing protocols and KPIs ready Result from partner PT. The result has been achieved on 30 June 2021 in month 7 of the project (results documented in report 2 and 3 of the planned result:… Read more
August 19, 2021 Milestone 1 (achieved) : Requirements and Specifications for Use cases defined Result from partner PT. The result has been achieved on 30 June 2021 in month 7 of the project (results documented in report 1 of the planned result: Hybrid Storage… Read more
July 26, 2021 Medium-fidelity battery cell testing finalized Result has been achieved on 3 June 2021 in month 7 of the project Read more
July 1, 2021 Detailed technical specifications for the Hybrid Battery Energy Storage System (HBESS) prototype Result from all partners. Read more
December 29, 2020 Start of the iSTORMY project: December 1st, 2020! On the first of December, 2020, the iSTORMY project started. The project is funded by the EC. Read more